A can do a work in 9 days. If B is 50% more efficient than A, then in how many days can B do the same work ?
A 13.5
B 4.5
C 6
D 5
answer is C. it has been proved in other sites as well....one day's work of A=1/9one day's work of B= 1/9 x 150/100 1/9 x 3/2 =1/6 work is completed in 6 days by B.