12 men can do a piece of work in 30 days. How many more men will be required to do it in 20 days?

A8
B6
C10
D7


Ans 1:

Class : Class 8
B

Ans 2:

Class : Class 8
B. 6

Ans 3:

Class : Class 8
B. 6

Ans 4:

Class : Class 8
Since it is in inverse proportion, 12:x::30:20 12×30=20x 360÷20=x x=18 More men= 18-12 =6 men more required